1.17.2007 On Rainbow Island, crews installed high strength geosynthetic fabric and fill was placed on top
1.17.2007 On Rainbow Island, crews installed high strength geosynthetic fabric and fill was placed on top
1.28.2008 A concrete I-beam is being lifted into place
1.28.2008 A concrete I-beam is being lifted into place
1.28.2008 Crews install steel sheeting for the west bulkhead on Rainbow Island
1.28.2008 Crews install steel sheeting for the west bulkhead on Rainbow Island
1.28.2008 Crews remove the temporary trestle on Elbow Thorofare
1.28.2008 Crews remove the temporary trestle on Elbow Thorofare
1.28.2008 Crews work on the demolition of the Route 52 bridge over Rainbow Channel with the newly constructed Route 52 northbound bridge deck on the far left
1.28.2008 Crews work on the demolition of the Route 52 bridge over Rainbow Channel with the newly constructed Route 52 northbound bridge deck on the far left
1.28.2008 Crews work on the demolition of the Route 52 bridge over Rainbow Channel with the newly constructed Route 52 northbound bridge deck on the far right
1.28.2008 Crews work on the demolition of the Route 52 bridge over Rainbow Channel with the newly constructed Route 52 northbound bridge deck on the far right
1.28.2008 Crews work on the Route 52 southbound bridge on Rainbow Island
1.28.2008 Crews work on the Route 52 southbound bridge on Rainbow Island
1.3.2007 Crews install cofferdam on Rainbow Channel
1.3.2007 Crews install cofferdam on Rainbow Channel
1.3.2007 STATNAMIC load testing is being performed on the VibroCore concrete shaft on Rainbow Island
1.3.2007 STATNAMIC load testing is being performed on the VibroCore concrete shaft on Rainbow Island
1.5.2007 VibroCore concrete shaft on Rainbow Island
1.5.2007 VibroCore concrete shaft on Rainbow Island
10.1.2007 This is a view of the Route 52 northbound roadway embankment on Rainbow Island
10.1.2007 This is a view of the Route 52 northbound roadway embankment on Rainbow Island
10.11.2006 Fill being placed to build temporary wall and ramp adjacent to the existing roadway at Elbow Island
10.11.2006 Fill being placed to build temporary wall and ramp adjacent to the existing roadway at Elbow Island
10.11.2006 Snooper truck is being used to provide access to the underside of the existing bridge
10.11.2006 Snooper truck is being used to provide access to the underside of the existing bridge
10.19.2006 The 80' long test pile is being lifted into position to be driven into the ground
10.19.2006 The 80' long test pile is being lifted into position to be driven into the ground
10.25.2006 Concrete pile being loaded on to a barge
10.25.2006 Concrete pile being loaded on to a barge
10.30.2006 80 foot test pile driven into the ground
10.30.2006 80 foot test pile driven into the ground
10.30.2006 Installation of coated permanent sheeting black adjacent to the temporary sheeting brown at the barge access area at Garrets Island
10.30.2006 Installation of coated permanent sheeting black adjacent to the temporary sheeting brown at the barge access area at Garrets Island
10.30.2006 Temporary retaining wall is being constructed to provide material storage and staging area at Garrets Island
10.30.2006 Temporary retaining wall is being constructed to provide material storage and staging area at Garrets Island
11.2.2006 The 115 foot long concrete pile is being prepared to be installed in Rainbow Channel
11.2.2006 The 115 foot long concrete pile is being prepared to be installed in Rainbow Channel
11.21.2007 Crews saw cut a concrete pile on Elbow Thorofare
11.21.2007 Crews saw cut a concrete pile on Elbow Thorofare
11.21.2007 Crews work on a concrete pour for the pile cap on Elbow Thorofare
11.21.2007 Crews work on a concrete pour for the pile cap on Elbow Thorofare
11.21.2007 The pier cap form work is installed on Elbow Thorofare
11.21.2007 The pier cap form work is installed on Elbow Thorofare
11.26.2007 The pier cap work is being lifted onto Elbow Thorofare
11.26.2007 The pier cap work is being lifted onto Elbow Thorofare
11.27.2007 The reinforcing steel for the pier cap is being lifted onto Elbow Thorofare
11.27.2007 The reinforcing steel for the pier cap is being lifted onto Elbow Thorofare
11.28.2006 Crews are installing a permanent retaining wall on Rainbow Island
11.28.2006 Crews are installing a permanent retaining wall on Rainbow Island
11.28.2006 Crews construct the retaining wall for the temporary ramp on Garrets Island
11.28.2006 Crews construct the retaining wall for the temporary ramp on Garrets Island
11.30.2007 Crews work on a concrete pour for the pile cap on Elbow Channel
11.30.2007 Crews work on a concrete pour for the pile cap on Elbow Channel
12.10.2007 Crews work on constructing the roadway on Rainbow Island
12.10.2007 Crews work on constructing the roadway on Rainbow Island
12.10.2007 The Route 52 northbound bridge deck over Rainbow Channel is open to traffic
12.10.2007 The Route 52 northbound bridge deck over Rainbow Channel is open to traffic
12.10.2007 The temporary ramp on Garrets Island is open to traffic
12.10.2007 The temporary ramp on Garrets Island is open to traffic
12.13.2006 The contractor is unloading concrete piles at the barge access area on Garretts Channel
12.13.2006 The contractor is unloading concrete piles at the barge access area on Garretts Channel
12.14.2006 Preparations are being made for the static load test of one of the piles at Rainbow Channel
12.14.2006 Preparations are being made for the static load test of one of the piles at Rainbow Channel
12.15.2006 View of the temporary bridge being used by the contractor across Elbow Thorofare
12.15.2006 View of the temporary bridge being used by the contractor across Elbow Thorofare
12.20.2006 Across from the existing Visitor Center on Garretts Island, the fill for the temporary ramp is being graded
12.20.2006 Across from the existing Visitor Center on Garretts Island, the fill for the temporary ramp is being graded
12.26.2006 A permanent Variable Message Sign will be installed at the Garden State Parkway
12.26.2006 A permanent Variable Message Sign will be installed at the Garden State Parkway
12.6.2007 Crews saw cut the bridge deck on the Route 52 northbound bridge
12.6.2007 Crews saw cut the bridge deck on the Route 52 northbound bridge
2.1.2007 Crews work on reinforcing the pier columns
2.1.2007 Crews work on reinforcing the pier columns
2.21.2007 Crews work on the construction of the cofferdam
2.21.2007 Crews work on the construction of the cofferdam
2.28.2007 On Rainbow Island, crews installed high strength geosynthetic fabric and fill was placed on top
2.28.2007 On Rainbow Island, crews installed high strength geosynthetic fabric and fill was placed on top
2.28.2007 On Rainbow Island, crews work on the concrete piles
2.28.2007 On Rainbow Island, crews work on the concrete piles
3.12.2007 Crews construct the VibroCore concrete shaft on Rainbow Island
3.12.2007 Crews construct the VibroCore concrete shaft on Rainbow Island
3.12.2007 Crews construct the VibroCore concrete shaft on Rainbow Island
3.12.2007 Crews construct the VibroCore concrete shaft on Rainbow Island
3.12.2007 Crews work on the construction of the VibroCore concrete shaft
3.12.2007 Crews work on the construction of the VibroCore concrete shaft
3.21.2007 On Garrets Island, formworks are readied for the pier cap installation
3.21.2007 On Garrets Island, formworks are readied for the pier cap installation
3.21.2012 The Rainbow Island Fishing north pier has a newly poured deck and decorative light fixtures
3.21.2012 The Rainbow Island Fishing north pier has a newly poured deck and decorative light fixtures
3.8.2012 This aerial view is of the project site looking south towards Ocean City.png
3.8.2012 This aerial view is of the project site looking south towards Ocean City.png
3.9.2007 On Rainbow Island, crews work on the construction of the footing
3.9.2007 On Rainbow Island, crews work on the construction of the footing
4.10.2007 On Rainbow Island, the pier cap formwork is constructed
4.10.2007 On Rainbow Island, the pier cap formwork is constructed
4.17.2007 On Rainbow Island, crews work on the concrete piles
4.17.2007 On Rainbow Island, crews work on the concrete piles
4.20.2007 Crews work on the construction of the bridge columns
4.20.2007 Crews work on the construction of the bridge columns
4.3.2007 Crews work on the geogrid layout
4.3.2007 Crews work on the geogrid layout
4.3.2007 On Rainbow Island, the swale is being constructed
4.3.2007 On Rainbow Island, the swale is being constructed
4.5.2007 On Rainbow Island, crews work on the construction of the pier cap.png
4.5.2007 On Rainbow Island, crews work on the construction of the pier cap.png
5.11.2007 Crews work on the installation of the pier cap form work on Garrets Island
5.11.2007 Crews work on the installation of the pier cap form work on Garrets Island
5.15.2007 On Rainbow Channel, the concrete piles are being installed
5.15.2007 On Rainbow Channel, the concrete piles are being installed
5.15.2007 This view is of the Route 52 north and southbound piers on Rainbow Channel
5.15.2007 This view is of the Route 52 north and southbound piers on Rainbow Channel
5.15.2007 This view is of the Route 52 northbound piers on Rainbow Channel
5.15.2007 This view is of the Route 52 northbound piers on Rainbow Channel
5.2.2007 On Rainbow Channel, the reinforcing steel for the pier cap is being installed
5.2.2007 On Rainbow Channel, the reinforcing steel for the pier cap is being installed
5.23.2007 Crews work on placing a 140 foot long I beam on Garrets Island
5.23.2007 Crews work on placing a 140 foot long I beam on Garrets Island
5.27.2012 This view is of the high level bridge over Beach Thorofare with the remains of the old structure in the foreground
5.27.2012 This view is of the high level bridge over Beach Thorofare with the remains of the old structure in the foreground
6.12.2007 Crews are constructing the bridge deck on Route 52 northbound
6.12.2007 Crews are constructing the bridge deck on Route 52 northbound
6.15.2007 The concrete I beam has been installed on one of the 14 spans over the Rainbow Channel
6.15.2007 The concrete I beam has been installed on one of the 14 spans over the Rainbow Channel
6.19.2007 Crews are working on constructing a temporary ramp
6.19.2007 Crews are working on constructing a temporary ramp
6.21.2007 Crews are constructing the bridge deck over Rainbow Channel
6.21.2007 Crews are constructing the bridge deck over Rainbow Channel
6.21.2007 Crews are working on constructing the retaining wall on Rainbow Island
6.21.2007 Crews are working on constructing the retaining wall on Rainbow Island
7.13.2007 View of the Route 52 northbound bridge on Rainbow Island
7.13.2007 View of the Route 52 northbound bridge on Rainbow Island
7.16.2007 Crews work on constructing a temporary ramp on Garrets Island
7.16.2007 Crews work on constructing a temporary ramp on Garrets Island
7.19.2007 A barge is delivering concrete for a pour on the Route 52 northbound bridge
7.19.2007 A barge is delivering concrete for a pour on the Route 52 northbound bridge
7.19.2007 Crews work on the concrete deck pour on the Route 52 northbound bridge
7.19.2007 Crews work on the concrete deck pour on the Route 52 northbound bridge
7.6.2007 Crews work to lift a concrete I beam into place
7.6.2007 Crews work to lift a concrete I beam into place
8.1.2006 A view of the field office area, looking east from Somers Point Circle
8.1.2006 A view of the field office area, looking east from Somers Point Circle
8.1.2006 A view of the field office complex, looking towards the bay from Somers Mansion
8.1.2006 A view of the field office complex, looking towards the bay from Somers Mansion
8.1.2007 Crews install steel reinforcement for the Route 52 southbound pier column on Rainbow Channel
8.1.2007 Crews install steel reinforcement for the Route 52 southbound pier column on Rainbow Channel
8.1.2007 This retaining wall with temporary drainage outfall pipe is on Rainbow Island
8.1.2007 This retaining wall with temporary drainage outfall pipe is on Rainbow Island
8.15.2007 View of the south abutment and Route 52 northbound bridge spans near Rainbow Island
8.15.2007 View of the south abutment and Route 52 northbound bridge spans near Rainbow Island
8.2.2006 The contractor's surveyor is operating a One Man Total Station Robotic Instrument
8.2.2006 The contractor's surveyor is operating a One Man Total Station Robotic Instrument
8.2.2006 The field office area is being set up adjacent to Goll Avenue, Shore Road and Somers Point Circle
8.2.2006 The field office area is being set up adjacent to Goll Avenue, Shore Road and Somers Point Circle
8.2.2006 The survey control is being verified on Garrets Island
8.2.2006 The survey control is being verified on Garrets Island
8.25.2007 Crews install battered piles on Rainbow Island
8.25.2007 Crews install battered piles on Rainbow Island
8.25.2007 Crews install concrete piles for the north abutment on Rainbow Island
8.25.2007 Crews install concrete piles for the north abutment on Rainbow Island
8.7.2007 View of the Route 52 northbound bridge span on Rainbow Channel
8.7.2007 View of the Route 52 northbound bridge span on Rainbow Channel
8.9.2007 This precast concrete deck panel is being installed on the Route 52 northbound bridge
8.9.2007 This precast concrete deck panel is being installed on the Route 52 northbound bridge
9.12.2007 Crews work on installing the reinforcing steel for the pier cap on Rainbow Channel
9.12.2007 Crews work on installing the reinforcing steel for the pier cap on Rainbow Channel
9.13.2007 Crews work on installing the diaphragm bars on the I-beams on the Route 52 northound bridge
9.13.2007 Crews work on installing the diaphragm bars on the I-beams on the Route 52 northound bridge
9.13.2007 Crews work on lifting a concrete I beam into place
9.13.2007 Crews work on lifting a concrete I beam into place
9.20.2007 Crews install concrete piles on Rainbow Channel
9.20.2007 Crews install concrete piles on Rainbow Channel
9.24.2007 Crews install bearing seats on a pier cap on Rainbow Channel
9.24.2007 Crews install bearing seats on a pier cap on Rainbow Channel
9.25.2007 Crews work on the Route 52 northbound bridge next to the southbound piers on Rainbow Channel
9.25.2007 Crews work on the Route 52 northbound bridge next to the southbound piers on Rainbow Channel
9.27.2006 Preparing to install temporary sheeting at Beach Thorofare barge access
9.27.2006 Preparing to install temporary sheeting at Beach Thorofare barge access
9.30.2007 Aerial views of the Route 52 Bridge construction on Rainbow Channel
9.30.2007 Aerial views of the Route 52 Bridge construction on Rainbow Channel
9.30.2007 Aerial views of the Route 52 Bridge construction on Rainbow Channel2
9.30.2007 Aerial views of the Route 52 Bridge construction on Rainbow Channel2
9.5.2007 This is a view of the Route 52 northbound bridge spans on Rainbow Channel
9.5.2007 This is a view of the Route 52 northbound bridge spans on Rainbow Channel
9.5.2007 This is a view of the Route 52 piers on Rainbow Channel
9.5.2007 This is a view of the Route 52 piers on Rainbow Channel
9.6.2007 Crews work on the concrete deck pour on the Route 52 northbound bridge
9.6.2007 Crews work on the concrete deck pour on the Route 52 northbound bridge